top of page
Writer's pictureZoe St Pierre

New Rules for Septic Tanks

Updated: Dec 20, 2018


If you have a septic tank that discharges directly to a water course, you will need to replace or upgrade your treatment system by 1 January 2020.


Use the correct treatment system

You must use a small sewage treatment plant to treat the sewage if you’re discharging to a surface water such as a river or stream. A small sewage treatment plant (also known as a package treatment plant) uses mechanical parts to treat the liquid so it’s clean enough to go into a river or stream.


Discharges from septic tanks directly to a surface water are not allowed under the general binding rules. If you have a septic tank that discharges directly to a surface water you will need to replace or upgrade your treatment system by 1 January 2020. Where properties with septic tanks that discharge directly to surface water are sold before 1 January 2020, responsibility for the replacement or upgrade of the existing treatment system should be addressed between the buyer and seller as a condition of sale.


If the Environment Agency finds evidence that your septic tank discharging to a surface water is causing pollution, you will need to replace or upgrade your system earlier than 1 January 2020. You will usually have to do this within 1 year, although this will be agreed on a case-by-case basis.


You may be able to:

connect to mains sewer – where available install a drainage field (also known as an infiltration system) so the septic tank can discharge to ground instead replace your septic tank with a small sewage treatment plant


You can apply for a permit for an existing or new discharge to a surface water from a septic tank. A permit is only granted in exceptional circumstances.


If you’re planning to use a septic tank conversion unit to upgrade an existing septic tank discharging to a surface water contact the Environment Agency to check it meets the required standard. You will be asked to provide evidence that it will treat to the equivalent standard as a sewage treatment plant. You will still need to apply for a permit.


Your treatment system must meet the right standards

Your treatment system must meet the relevant British Standard which was in force at the time of installation. The standards currently in force for new systems are:

BS EN 12566 for small sewage treatment plantsBS 6297:2007 for drainage fields


Your treatment plant met the British Standard in place at the time of installation if:

it has a CE Mark, the manual or other documentation that came with your tank or treatment plant has a certificate of compliance with a British Standards.


You can also ask the company that installed your equipment to confirm that it complies with the British Standard that was in place at the time the equipment was installed. If there were no British Standards in place when your treatment system was installed (that is before 1983) you do not need to do anything else to meet this requirement.


Your treatment system must be installed properly and have enough capacity

Your treatment system must be large enough to handle the maximum amount of sewage it will need to treat. If you install a new small sewage treatment plant you must check with the installer that it meets the sizing requirements in British Water Flows. If the amount of sewage the system needs to treat increases (for example, because you’ve extended your property or connected an additional property) you must make sure the treatment system is still big enough. You must also recalculate the maximum daily volume of your discharge and apply for a permit if it is more than 5 cubic metres (5,000 litres) a day.

Your treatment system must be installed in line with the manufacturer’s specification (the instruction manual or technical set of requirements that comes with the equipment).

If you’re in a tidal area (an area where the water level changes according to tides), you must make sure the top end of the pipe that releases sewage is below the ‘mean low water spring mark’. This is the average low water mark at the time of spring tides.


Have your treatment system regularly emptied and maintained

You must get the sludge which builds up in your sewage treatment plant removed (desludged) before it exceeds the maximum capacity. As a minimum, you should have your treatment system desludged once a year or in line with the manufacturer’s instructions.

The company you use to dispose of your waste sludge must be a registered waste carrier. Ask the company to confirm this when you arrange to have your tank emptied or ask the tanker driver for a copy of the company’s waste carrier’s certificate.

You should have your treatment system regularly maintained in line with the manufacturer’s instructions. If these are not available, ask your local maintenance company for advice.

You must have your treatment system repaired or replaced if it is not in good working order.


You sell your property - tell the new owner about the sewage treatment system

If you sell your property, you must tell the new operator (the owner or person responsible for the sewage treatment plant) in writing that a sewage discharge is in place.

Include:

a description of the treatment plant and drainage system

the location of the main parts of the treatment plant, drainage system and discharge point details of any changes made to the treatment plant and drainage system details of how the treatment plant should be maintained, and the maintenance manual if you have one plus maintenance records if you have them.


You stop using your treatment system - make sure it’s properly decommissioned

You must remove anything that could cause pollution (for example, remaining sludge) when you stop using a septic tank or sewage treatment plant.

This does not apply if you only stop using the equipment temporarily, for example if your property is empty.

You can ask a maintenance company for advice on how to decommission your septic tank or treatment plant properly.


Additional rules for new treatment systems installed and in use on or after 1 January 2015

You must follow these additional rules if you:

started a new discharge from a small sewage treatment plant on or after 1 January 2015 had a discharge to ground before 1 January 2015 which you now want to change to discharge to a surface water (or the other way round)

had a discharge to a surface water before 1 January 2015 and you want to install a new drainage pipe which discharges more than 10 metres away from the existing one or which goes to a different surface water.


Check if there’s a public sewer nearby

If any part of the building your treatment plant serves is within 30 metres of a public sewer, the Environment Agency will not allow you to start a new discharge from a sewage treatment plant under the general binding rules.

If you are building a development of more than one property, this distance must be multiplied by the number of properties. For example, if there are 3 properties then the distance will be 3 x 30 metres = 90 metres.


To find out if there is a public sewer near your property, contact your local water company.

If there is a good reason why you cannot connect to the sewer (for example, there is a river or a hill in the way) then you must apply for a permit so that the Environment Agency can decide whether to allow you to use a sewage treatment plant instead.


Building regulations and planning approval

You must have planning permission and Building Regulations Approval if you have or are planning to install a new sewage treatment plant.


Check if the discharge point is in or near a designated sensitive area

If you have or are planning to start a new discharge to a surface water in or near to a designated sensitive area, you must apply for a permit.


Make sure the surface water has flow

New discharges are not allowed to a ditch or a surface water that does not contain flowing water throughout the whole year. That is unless there is a drought or an unusually long period of dry weather.

New discharges to watercourses that seasonally dry up are not allowed under the general binding rules, nor are discharges to enclosed lakes or ponds.


Using a partial drainage field - check it meets the requirements

A partial drainage field (also known as a seasonal soakaway) is a system for discharging to water which allows effluent to drain into the ground when levels in the watercourse are low, and into the watercourse when groundwater levels are high.

If you’re using a partial drainage field for a new discharge, you must install it within 10 metres of the edge of the watercourse and you must only use it with a small sewage treatment plant, not a septic tank.


Contact the Environment Agency if you are not sure on any of the above points.



Comments


bottom of page